How do you change duration default to days?

Member for

19 years 10 months

Hi Dan - Welcome to planning plannet.

Right Click on the top of the duration column.

Select Table definition

Select duration in the dropdown

In the right hand panel find Overide Time Unit and select the one you want.

Best regards

Mike Testro