Library Explorer > Code Library > Code Group > Name any code you like and give it a colour. Then drag and drop onto selected tasks. Use codes to filter. Avoid creating multiple colours and pattens or your chart will look like a fireworks display.
Notes on Tasks
Insert > Text Annotation > Drag to Task > Type Note
Or set up a user field
Or Right Click task > Properties > Status > Type note
Roll up tasks - I think you are referring to "Task per Line" mode
Each task has an individual name but the bar has the control name for the cascade. The easiest way to roll up or down is the little plus sign on the extreme left hand column.
I hope that helps.
Best regards
Mike T.
BTW all of this can be found on the help section F1.
Member for
11 yearsThank You Mike!It Really
Thank You Mike!
It Really Helped!
That really helped. Sorry for bothering I am catching up with tutorials every day.
Have a nice week!
Karina
Member for
19 years 10 monthsHi KarinaActivity
Hi Karina
Activity Codes
Library Explorer > Code Library > Code Group > Name any code you like and give it a colour. Then drag and drop onto selected tasks. Use codes to filter. Avoid creating multiple colours and pattens or your chart will look like a fireworks display.
Notes on Tasks
Insert > Text Annotation > Drag to Task > Type Note
Or set up a user field
Or Right Click task > Properties > Status > Type note
Roll up tasks - I think you are referring to "Task per Line" mode
Each task has an individual name but the bar has the control name for the cascade. The easiest way to roll up or down is the little plus sign on the extreme left hand column.
I hope that helps.
Best regards
Mike T.
BTW all of this can be found on the help section F1.