Asta Powerproject Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2012-08-07 09:46 Permalink Hi Chris Alternatively create Hi Chris Alternatively create a dummy cost item at £1.00. Best regards Mike Testro Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Mon, 2012-08-06 14:35 Permalink Create a Dummy Resource, make Create a Dummy Resource, make it to be a non-leveling resource and assign a unit of this resource to all activities then the histogram for this resource shall display what you are looking for. Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2012-08-07 09:46 Permalink Hi Chris Alternatively create Hi Chris Alternatively create a dummy cost item at £1.00. Best regards Mike Testro
Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Mon, 2012-08-06 14:35 Permalink Create a Dummy Resource, make Create a Dummy Resource, make it to be a non-leveling resource and assign a unit of this resource to all activities then the histogram for this resource shall display what you are looking for.
Member for
19 years 10 monthsHi Chris Alternatively create
Hi Chris
Alternatively create a dummy cost item at £1.00.
Best regards
Mike Testro
Member for
21 years 8 monthsCreate a Dummy Resource, make
Create a Dummy Resource, make it to be a non-leveling resource and assign a unit of this resource to all activities then the histogram for this resource shall display what you are looking for.