Histogram To Count Tasks

Member for

19 years 10 months

Hi Chris

Alternatively create a dummy cost item at £1.00.

Best regards

Mike Testro

Member for

21 years 8 months

Create a Dummy Resource, make it to be a non-leveling resource and assign a unit of this resource to all activities then the histogram for this resource shall display what you are looking for.