This is almost always down to restricted access to the \Project \Template folders in the install folder.

Change these to Full Control and you should be OK.



The one advantag eof the Template route (rather than Mike’s Copy/Paste) is that it sets "Week 1" on the Date Zone in all Views of the project.

Just saves you a little hassle at set-up time.

Member for

17 years 3 months



Mike,



Practical approach as ever !!



Ken

Member for

19 years 10 months

Hi Ken



I create a standard bar chart for a particular type of project with set up calendars - resources - work patterns etc.



When a new programme is required I just copy the chart and save as required.



Then adjust for the new start dates etc and start adding tasks.



I never use the wizards but set up a bespoke base evry time.



Best regards



Mike Testro