I usually use the internal project reference number, an alphanumeric identifier such as CP for construction, IMP for integrated master, then a number starting at 01, then the revision number, then the date in reverse order, so
C26785/IMP/01 - Rev 01 070706
This way the latest programme is always at the bottom of the list.
Member for
22 years 4 monthsRE: What do you call / how do you name your projects ?
thanks Nieman. seems sensible enough for me !
Member for
18 years 7 monthsRE: What do you call / how do you name your projects ?
I usually use the internal project reference number, an alphanumeric identifier such as CP for construction, IMP for integrated master, then a number starting at 01, then the revision number, then the date in reverse order, so
C26785/IMP/01 - Rev 01 070706
This way the latest programme is always at the bottom of the list.