What do you call / how do you name your projects ?

Member for

18 years 7 months

I usually use the internal project reference number, an alphanumeric identifier such as CP for construction, IMP for integrated master, then a number starting at 01, then the revision number, then the date in reverse order, so



C26785/IMP/01 - Rev 01 070706



This way the latest programme is always at the bottom of the list.