Oracle Primavera - PM6 Member for 14 years 7 months Member for 14 years 7 months Submitted by renzo00 on Wed, 2024-08-21 07:48 Permalink Hi:for the software Hi: for the software Primavera, actual regular units (for labor resource, as m-h) correspond to non-overtime worked. Actual units include the overtime units. Useful to differentiate for costs purposes (it possible to limit the regular units and set a different price -factor- for overtime). regards Log in or register to post comments
Member for 14 years 7 months Member for 14 years 7 months Submitted by renzo00 on Wed, 2024-08-21 07:48 Permalink Hi:for the software Hi: for the software Primavera, actual regular units (for labor resource, as m-h) correspond to non-overtime worked. Actual units include the overtime units. Useful to differentiate for costs purposes (it possible to limit the regular units and set a different price -factor- for overtime). regards
Member for
14 years 7 monthsHi:for the software
Hi:
for the software Primavera, actual regular units (for labor resource, as m-h) correspond to non-overtime worked.
Actual units include the overtime units.
Useful to differentiate for costs purposes (it possible to limit the regular units and set a different price -factor- for overtime).
regards