Multiple imports of risks to Primavera P6

Member for

1 year 5 months

Hello Dejan,

 

I think currently, Primavera (P6) does not natively support exporting and importing risks directly through Excel in the same way it does for activities and resources. To achieve this, you typically need to manage risks within P6 itself rather than using Excel as an intermediary for direct risk import.

 

Hope it would help you.