The WBS summary activity functions more like a "hammock" activity, summarizing the activities within the WBS element it represents. While it can be linked to other activities for dependencies, it doesn't directly influence the scheduling or sequencing of those activities, unlike MS Project, where the summary bar can drive activity when linked to a network or used as a predecessor.
Member for
9 years 8 monthsno! WBS summary activities
no!
WBS summary activities and LoE activities can have no schedule impact, and cannot be levelled
Member for
19 yearsHi Rod,The WBS summary
Hi Rod,
The WBS summary activity functions more like a "hammock" activity, summarizing the activities within the WBS element it represents. While it can be linked to other activities for dependencies, it doesn't directly influence the scheduling or sequencing of those activities, unlike MS Project, where the summary bar can drive activity when linked to a network or used as a predecessor.