A get-around is to break the logic and recalculate then put the logic back in. If that doesn't work, copy the LOE without logic and add the logic to the copy.
Member for
16 years 1 month
Member for16 years1 month
Submitted by Chris Gibbons on Wed, 2024-01-24 11:48
A get-around is to break the logic and recalculate then put the logic back in. If that doesn't work, copy the LOE without logic and add the logic to the copy.
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Tue, 2020-03-24 12:05
Member for
16 years 1 monthThis can happen with LOE's in
This can happen with LOE's in the same project too. A get-around is to break the logic to the LOE and put it back in
Member for
16 years 1 monthA get-around is to break the
A get-around is to break the logic and recalculate then put the logic back in. If that doesn't work, copy the LOE without logic and add the logic to the copy.
Member for
16 years 1 monthA get-around is to break the
A get-around is to break the logic and recalculate then put the logic back in. If that doesn't work, copy the LOE without logic and add the logic to the copy.
Member for
16 years 3 monthsmake sure that the schedule
make sure that the schedule options in the gneral tab that Ignore relationships to and from other projects is NOT checked.
also in the same window at the bottom make sure that calculate float based on finish date of Each project instead of Opened projects.
if that does not work then chnage it to calculate float based on finish date of Opened projects and then open the project and calculate the schedule.