Critical activities with Negative float

Member for

14 years 2 months

Highest negative number may not solve your problem as real critical activities may have FT with less negative number.  

For effective project management you need to be able to identify REAL critical path. 

I have offered a solution in this post:

https://saluteenterprises.com.au/total-floats-with-or-without-project-d…

 

Regards,

Alex Lyaschenko

Member for

14 years 2 months

Highest negative number may not solve your problem as real critical activities may have FT with less negative number.  

For effective project management you need to be able to identify REAL critical path. 

I have offered a solution in this post:

https://saluteenterprises.com.au/total-floats-with-or-without-project-d…

 

Regards,

Alex Lyaschenko

Member for

14 years 2 months

Highest negative number may not solve your problem as real critical activities may have FT with less negative number.  

For effective project management you need to be able to identify REAL critical path. 

I have offered a solution in this post:

https://saluteenterprises.com.au/total-floats-with-or-without-project-d…

 

Regards,

Alex Lyaschenko