The solution to your problem is to break it with the milestone activity so the float will be calculated correctly as long as the multiple calendar had the same start hours and same finish hours.
Example: Act 1 = 7d x 8h workweek = 5 days duration (start on Monday finish Friday) link FS (successor) to Act 2 = 5d x 8h workweek, the float will be calculated resulting 2 days float because act 2 will start on Monday. To resolve this issue, you have to link FF to a Finish Milestone with 5d x8h day workweek calendar then link FS to Act 2 with 5d x 8h workweek and it will be calculated as 0 float.
Member for
18 years 5 months
Member for18 years5 months
Submitted by Chris Lothian on Tue, 2023-05-16 11:13
Member for
16 years 3 monthshere is what I do in a
here is what I do in a situation like that
create a new activity code call it My Path and give it a value code of CP Critical path
next add that column to the data area on the left
next filter for the last activity in the Project ONLY
in the predcessor tab at the bottom right click and select Customize Predcessor Columns
Expand the General category on the left
bring the Critical and Driving selection to the right to be displayed
Next look of the predcessor that has BOTH driving and critical boxes checked
select that activity that has both boxes checked and at the bottom select GoTo
(if there are 2 or more activities that have both boxes checked select the one with the least amount of total float)
this will add that activity into the current view
keep doing this until you gate back to the data date
now select edit and then Select All (or do a fill down for the Activity code that you just added)
right click and select Assign
Then select activity codes and assign all of these activities to the new codes call My Path and give them the code value of CP
Now filter where for activity code
Where My Path equals CP
this is your most critical path through the project
Member for
19 yearsHi Chris,The solution to your
Hi Chris,
The solution to your problem is to break it with the milestone activity so the float will be calculated correctly as long as the multiple calendar had the same start hours and same finish hours.
Example: Act 1 = 7d x 8h workweek = 5 days duration (start on Monday finish Friday) link FS (successor) to Act 2 = 5d x 8h workweek, the float will be calculated resulting 2 days float because act 2 will start on Monday. To resolve this issue, you have to link FF to a Finish Milestone with 5d x8h day workweek calendar then link FS to Act 2 with 5d x 8h workweek and it will be calculated as 0 float.