Facing problem in Variance - BL project finish date in P6

Member for

19 years

Hi Muhammad,

P6, same most of the other Scheduling Software calculate duration and variance base on working days and not calendar days.

Member for

8 years 11 months

Hi Rodel Marasigan,

Thanks for explaination.My calendar is 6-days a week.

Is there any column selection to check the difference in calendar days instead of deducting 8 days of Non-Work days.

Regards,

Member for

19 years

Muhammad,

There are two things that may affect the calculation of BL variance in P6.

1) Calendar working days - If you have a 6 days a week working days (Mon-Sat) on your calendar then the calculation is correct. The answer is 53 instead of 61.

2) Earned Value settings in Admin Preference - By default, P6 is calculating Earned Value BL variance based on:

   * Budgeted Values with Planned Date - Meaning the variance calculated on BL Planned Date vs Current Date. If the Baseline is progress Baseline and not fresh "no progress baseline", the BL Planned date maybe different from BL Current Date. If the baseline is progressed then the Earned Value settings must change to At Completion Value with Current Date or Budgetted Values with Current Date.

Member for

8 years 11 months

Hi,

I accidently posted multiple time due to internet issue. ho wto delete the extra posts.

Member for

8 years 11 months

Hi,

I accidently posted multiple time due to internet issue. ho wto delete the extra posts.

Member for

8 years 11 months

Hi,

I accidently posted multiple time due to internet issue. ho wto delete the extra posts.