Would everyone here use a 3/1 data date for February progress?

Member for

19 years

The recommended and standard practice of data date is last working date and time of the reporting cycle.

Ex: Weekly cut-off = every Friday Cut-off at last working time say 5:00PM 

     Bi-weekly cut-off = alternate Friday Cut-off at last working time say 5:00PM

     Monthly cut-off = Last Friday of the Month at last working time say 5:00PM

     Shutdown per shift = Say at every 6:00PM 1st Shift and 6:00AM 2nd Shift