Oracle Primavera - PM6 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Wed, 2023-03-01 07:02 Permalink The recommended and standard The recommended and standard practice of data date is last working date and time of the reporting cycle. Ex: Weekly cut-off = every Friday Cut-off at last working time say 5:00PM Bi-weekly cut-off = alternate Friday Cut-off at last working time say 5:00PM Monthly cut-off = Last Friday of the Month at last working time say 5:00PM Shutdown per shift = Say at every 6:00PM 1st Shift and 6:00AM 2nd Shift Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Wed, 2023-03-01 07:02 Permalink The recommended and standard The recommended and standard practice of data date is last working date and time of the reporting cycle. Ex: Weekly cut-off = every Friday Cut-off at last working time say 5:00PM Bi-weekly cut-off = alternate Friday Cut-off at last working time say 5:00PM Monthly cut-off = Last Friday of the Month at last working time say 5:00PM Shutdown per shift = Say at every 6:00PM 1st Shift and 6:00AM 2nd Shift
Member for
19 yearsThe recommended and standard
The recommended and standard practice of data date is last working date and time of the reporting cycle.
Ex: Weekly cut-off = every Friday Cut-off at last working time say 5:00PM
Bi-weekly cut-off = alternate Friday Cut-off at last working time say 5:00PM
Monthly cut-off = Last Friday of the Month at last working time say 5:00PM
Shutdown per shift = Say at every 6:00PM 1st Shift and 6:00AM 2nd Shift