Microsoft Project Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Tue, 2023-02-28 01:13 Permalink In MSP the % Complete is In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6. Regatrds Paul E Harris Eastwood Harris Pty Ltd www.eh.com.au Log in or register to post comments
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Tue, 2023-02-28 01:13 Permalink In MSP the % Complete is In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6. Regatrds Paul E Harris Eastwood Harris Pty Ltd www.eh.com.au
Member for
24 years 6 monthsIn MSP the % Complete is
In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6.
Regatrds
Paul E Harris
Eastwood Harris Pty Ltd
www.eh.com.au