SS & FF Relationship

Member for

3 years 3 months

Thanks all for recommendation but this activity is not an overhead. Its is task dependent and can be on CP with resource assigned to it.. The tricky part is, it dpendent on the 2 activities above it. So, in simple terms i need to relate it with the earliest start & latest finish of either of the above 2 activities.

Member for

9 years 8 months

LoE activities are terrific for 'overhead' costs and resources, and even better for collecting timesheet data that has not got any activity ID information. You cannot level the resources.

Member for

19 years

Of course you can use LOE for resource loading. It is a logical way of resource loading such as prelims, engineering, constuction supports, equipment usage and or summary level of resouces.

Member for

3 years 3 months

Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.

Member for

3 years 3 months

Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.

Member for

3 years 3 months

Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.

Member for

19 years

The only way is to use LOE as per below:

A1170 - LOE Activity

Predecessor  A1130  SS

Successor A1160 FF