Gant baseline and actual date icons for each task

Member for

20 years 6 months

Joshua,

Where you select bars, you need to create a new one that uses the BL Project Start and BL Project Finish date fields and it will display the dates from whichever project you have assigned as the "Project Baseline" in the Assign Baselines option.

Member for

19 years

Just create another milestone on Bar Style format using Actual Start and Actual Finish.