Where you select bars, you need to create a new one that uses the BL Project Start and BL Project Finish date fields and it will display the dates from whichever project you have assigned as the "Project Baseline" in the Assign Baselines option.
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Fri, 2022-07-29 12:14
Member for
20 years 6 monthsJoshua,Where you select bars,
Joshua,
Where you select bars, you need to create a new one that uses the BL Project Start and BL Project Finish date fields and it will display the dates from whichever project you have assigned as the "Project Baseline" in the Assign Baselines option.
Member for
19 yearsJust create another milestone
Just create another milestone on Bar Style format using Actual Start and Actual Finish.