if an activty is complete it still has an original late date even thought this is no longer part of the total float calculations. However if activities are in progress its has a remaining late finsh date. For activites that are COMPLETED there is not and Remaining Late Finish date so it might be best to show the remaining late finish date column.
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Wed, 2022-07-20 10:27
Member for
16 years 3 monthsif an activty is complete it
if an activty is complete it still has an original late date even thought this is no longer part of the total float calculations. However if activities are in progress its has a remaining late finsh date. For activites that are COMPLETED there is not and Remaining Late Finish date so it might be best to show the remaining late finish date column.
Member for
19 yearsIf the activity is complete
If the activity is complete there is no remaining late date. If the activity is in progress with float then it has remaining late dates.