Owner looked at schedule and asked why there were late dates on items with Actuals - what do you say? what do you do?

Member for

16 years 3 months

if an activty is complete it still has an original late date even thought this is no longer part of the total float calculations. However if activities are in progress its has a remaining late finsh date. For activites that are COMPLETED there is not and Remaining Late Finish date so it might be best to show the remaining late finish date column. 

Member for

19 years

If the activity is complete there is no remaining late date. If the activity is in progress with float then it has remaining late dates.