Owner caused delay - most basic cost %?

Member for

12 years 5 months

I see delay settlements for general overhead - I thought it was fairly common.  I do not quite understand what you are saying, is there something out that supports that?

Member for

19 years 10 months

Hi John

General Head Office overhead costs are not claimable under the contract unless  you can show lack of turnover affected recovery using either a Hudson or Emden formula.

A single delay of 30 days is not sufficient.

Best regards Mike T.

Member for

12 years 5 months

7%.  I think most people would say check the contract...I assume it does not always say.