Donot delete activities (E&P) initially. Export all activities (E&P) with successor relationship. You will get construction activities having atleast one Engg/Proc predessor.
Take the successor column & add a temporary activity code (Please add the same code in P3 file).
Import the file in P3 & select activities having this code.
Those Construction activities are the ones without predessor (E&P).
Please note that those activities having Constrn activities as predessor will also appear. (e.g Installation of Equipment will have , 1) delivery of eqpt & 2) foundation of Eqpt as predessor. So take this into consideration.
Member for
22 years 6 monthsRE: filter for open ends !?
Its somewhat lengthy.
Donot delete activities (E&P) initially. Export all activities (E&P) with successor relationship. You will get construction activities having atleast one Engg/Proc predessor.
Take the successor column & add a temporary activity code (Please add the same code in P3 file).
Import the file in P3 & select activities having this code.
Those Construction activities are the ones without predessor (E&P).
Please note that those activities having Constrn activities as predessor will also appear. (e.g Installation of Equipment will have , 1) delivery of eqpt & 2) foundation of Eqpt as predessor. So take this into consideration.
Regards
Dattatreya Sriniwas