I know I know, but it's one of those things I'm sure we've never seen our system do before. Usually we've had to sort the remaining and costs ourselves. Logically it makes sense, we've just got to sort the costs before pushing the button.
Thank you as always for being the voice of reason.
Thom
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Thu, 2022-03-17 11:56
That is correct. P6 will automatically removed remaining Cost and remaining Unit when actualised the finished date. If you have actualised the cost and units to less or greater than budgeted unit / cost then tick the actual finished date, therefore what ever remaining unit/ cost will be removed. The main reason is if the Activity is completed then no more remaining duration. It's self explanatory. If no more remaining duration, therefore no duration left to hold the remaining cost/ unit. You cannot assume 0 duration can hold cost or unit.
Member for
16 years 3 monthsyou can change it if you want
you can change it if you want to
Member for
19 years 1 monthZoltan, I knew there was a
Zoltan,
I knew there was a setting somewhere for it, thank you for that but I take your point about done is done.
cheers
Thom
Member for
19 years 1 monthZoltan, I knew there was a
Zoltan,
I knew there was a setting somewhere for it, thank you for that but I take your point about done is done.
cheers
Thom
Member for
16 years 3 monthsif you do not want to do this
if you do not want to do this then turn the setting off
go to projects directory
then the calculations tab
on the right resource assignments
under when updaing Actual units or costs uncheck Recalculate Actual Units and costs whne duration % complete changes
Member for
19 years 1 monthHi Zoltan, I know I know, but
Hi Zoltan,
I know I know, but it's one of those things I'm sure we've never seen our system do before. Usually we've had to sort the remaining and costs ourselves. Logically it makes sense, we've just got to sort the costs before pushing the button.
Thank you as always for being the voice of reason.
Thom
Member for
16 years 3 monthsdone is done why would you
done is done why would you have any remaining unless you completed it in less time than planned ?
Member for
16 years 3 monthsdone is done why would you
done is done why would you have any remaining unless you completed it in less time than planned ?
Member for
19 yearsHi Thomas,That is correct. P6
Hi Thomas,
That is correct. P6 will automatically removed remaining Cost and remaining Unit when actualised the finished date. If you have actualised the cost and units to less or greater than budgeted unit / cost then tick the actual finished date, therefore what ever remaining unit/ cost will be removed. The main reason is if the Activity is completed then no more remaining duration. It's self explanatory. If no more remaining duration, therefore no duration left to hold the remaining cost/ unit. You cannot assume 0 duration can hold cost or unit.