1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units toOriginal
2. Choose View, Columns and add the columns for Actual Labor Units, Actual NonlaborUnits.
3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule.To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.
4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities inthis column and choose Edit, Fill Down.
5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activitiesin this column and choose Edit, Fill Down.
6. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.
7. Run the 2nd global change which sets the activity status to Not Started. 1st Global Change:
Subject Area: Activity Resource Assignments If: Where Resource Type equals Material
Then: Actual Material Units = 0
2nd Global change
Subject Area: Activities If: Where Activity Status is not equal to Not Started
highlight the activity you want to change, go to the status tab, uncheck the finish date, change the physical % complete back to zero, reset the actual & remaining labor units (budgeted quantity)in the labour units box, then you should be able to uncheck the start date, it will ask you Are you sure that you want to change the activity to be Not Started? Jusk click yes and it should work
Member for
14 years 11 monthsChange Actual Labor Units and
Change Actual Labor Units and Actual Nonlabor Units to zero.
You can do this with a global change, by adding columns, or in the status tab switching between Labor Units and Nonlabor using the drop down arrow:
[[wysiwyg_imageupload:8820:]]
Member for
16 years 3 monthsHow to de-status a schedule1.
How to de-status a schedule
1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units toOriginal
2. Choose View, Columns and add the columns for Actual Labor Units, Actual NonlaborUnits.
3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule.To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.
4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities inthis column and choose Edit, Fill Down.
5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activitiesin this column and choose Edit, Fill Down.
6. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.
7. Run the 2nd global change which sets the activity status to Not Started. 1st Global Change:
Subject Area: Activity Resource Assignments If: Where Resource Type equals Material
Then: Actual Material Units = 0
2nd Global change
Subject Area: Activities If: Where Activity Status is not equal to Not Started
Then: Activity Status Equals Not Started
Member for
10 years 2 monthsHi,Quick and easy way to
Hi,
Quick and easy way to remove actuals using only 1 Global Change.
Check out my articel here
https://www.linkedin.com/pulse/quick-way-remove-actuals-from-p6-schedul…
Member for
15 years 8 monthsHi,I write an article
Hi,
I write an article regarding How to remove actual / progress from Primavera P6 schedule.
If you're interested, kindly read it here https://doduykhuong.wordpress.com/2016/08/01/how-to-remove-actual-progress-from-primavera-p6-schedule/
Cheer
Member for
16 years 3 monthshere is a link to the
here is a link to the detailed instructions on how to do this
http://pmsite.com/forums/viewthread/3064/
Member for
18 yearsRE: Remove actuals in P6 (HELP)
Thanks Scott, yeah it worked.PP rocks!
Member for
20 years 7 monthsRE: Remove actuals in P6 (HELP)
highlight the activity you want to change, go to the status tab, uncheck the finish date, change the physical % complete back to zero, reset the actual & remaining labor units (budgeted quantity)in the labour units box, then you should be able to uncheck the start date, it will ask you Are you sure that you want to change the activity to be Not Started? Jusk click yes and it should work
Hope this helps,
Scott