check the detail of the calendar for each work day. It appears that one of the days is set to work less than 8 hours per day. Fix the calendar then group and sort by duration. make sure that auto reorganize is off then where the durations are less then a whole day fix the first one on that group and then do a fill down in the duration column within that grouping.
Member for
20 years 6 months
Member for20 years6 months
Submitted by Santosh Bhat on Mon, 2022-01-31 00:40
When you create an activity in P6, by default P6 calculates all duration in hours. This is where the settings in the calendars for work hours/time period are important. If your calednars was originally set such that 1day = 7hrs, then create a task as 5days, P6 will convert this to being a 35hr task.
This duration is then stored and any changes to the calendar do not automatically re-calculate existing durations.
When you change the calendars work hours/time period, P6 remembers that the task is 35hrs long, and now on a 8hrs/day calendar, this works out to be 35/8 = 4.375days.
The easiest way to resolve this is to run a Global Change to modify the durations of all tasks using that calendar (by setting up a condition in the Global change where Calendar = {name}). Then calculate that remaining duration = remaining duration * 1.14 - that is 8/7. However this may cause problems on activities that were created/modified AFTER the calendars work hours/time were changed.
Member for
19 years 7 months
Member for19 years7 months
Submitted by Frederic Fasquelle on Sun, 2022-01-30 14:35
You need to checked the time period settings on the project calendar that you used as default assignment for your new activities. It should match the calendar settings. If you default project calendar is 8h/day then the time period should be 8h/d. Once it is matched then checked the default duration from admin preference under general tab. It should also say 5 and not 4.4. The default duration also sometime change if the time duration under admin preference are change to different setting and must always check and make sure the Used assignned calendar to specify the number of work hours for its time period is tick.
Member for
16 years 3 monthscheck the detail of the
check the detail of the calendar for each work day. It appears that one of the days is set to work less than 8 hours per day. Fix the calendar then group and sort by duration. make sure that auto reorganize is off then where the durations are less then a whole day fix the first one on that group and then do a fill down in the duration column within that grouping.
Member for
20 years 6 monthsWhen you create an activity
When you create an activity in P6, by default P6 calculates all duration in hours. This is where the settings in the calendars for work hours/time period are important. If your calednars was originally set such that 1day = 7hrs, then create a task as 5days, P6 will convert this to being a 35hr task.
This duration is then stored and any changes to the calendar do not automatically re-calculate existing durations.
When you change the calendars work hours/time period, P6 remembers that the task is 35hrs long, and now on a 8hrs/day calendar, this works out to be 35/8 = 4.375days.
The easiest way to resolve this is to run a Global Change to modify the durations of all tasks using that calendar (by setting up a condition in the Global change where Calendar = {name}). Then calculate that remaining duration = remaining duration * 1.14 - that is 8/7. However this may cause problems on activities that were created/modified AFTER the calendars work hours/time were changed.
Member for
19 years 7 monthsHI,All settings of my project
HI,
All settings of my project calendar are good.
My only issue is regarding the admin preference available under P6 WEB, which is 7h/d.
If I modified it to 8h/d, all projects under my database will be affected and this is clearly not possible.
If there is no other solution, I will continue to modify manually the calendar.
Member for
19 yearsFrederic,You need to checked
Frederic,
You need to checked the time period settings on the project calendar that you used as default assignment for your new activities. It should match the calendar settings. If you default project calendar is 8h/day then the time period should be 8h/d. Once it is matched then checked the default duration from admin preference under general tab. It should also say 5 and not 4.4. The default duration also sometime change if the time duration under admin preference are change to different setting and must always check and make sure the Used assignned calendar to specify the number of work hours for its time period is tick.