Asta Powerproject Member for 19 years 7 months Member for 19 years 8 months Submitted by Konstantinos P… on Thu, 2022-01-27 17:01 Permalink Dariusz,You can if you make a Dariusz, You can if you make a small compromise and that is not showing the completed tasks under an incomplete summary. The filter would be [[wysiwyg_imageupload:8036:]] Criteria 1 - Summary Tasks with Task Progress Completed Criteria 2 - Tasks or Milestones or Summary Tasks with Task Progress Specific Progress Amount Less Than 100% Also, Objects must meet ANY criteria Otherwise, I'm sure you could write an SQL statement but not sure I can help you with that. Let me know if that works for you. Kind regards, Konstantinos Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2022-01-11 13:52 Permalink Sorry DariuszYou have to do Sorry Dariusz You have to do it manually. One Click and save is all you need. You don't have to show all your sub tasks. You can have a sub summary labelledd 100% and move every complted task down into that showing only the work in prgress. Best regards Mike T. Log in or register to post comments
Member for 19 years 7 months Member for 19 years 8 months Submitted by Konstantinos P… on Thu, 2022-01-27 17:01 Permalink Dariusz,You can if you make a Dariusz, You can if you make a small compromise and that is not showing the completed tasks under an incomplete summary. The filter would be [[wysiwyg_imageupload:8036:]] Criteria 1 - Summary Tasks with Task Progress Completed Criteria 2 - Tasks or Milestones or Summary Tasks with Task Progress Specific Progress Amount Less Than 100% Also, Objects must meet ANY criteria Otherwise, I'm sure you could write an SQL statement but not sure I can help you with that. Let me know if that works for you. Kind regards, Konstantinos
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2022-01-11 13:52 Permalink Sorry DariuszYou have to do Sorry Dariusz You have to do it manually. One Click and save is all you need. You don't have to show all your sub tasks. You can have a sub summary labelledd 100% and move every complted task down into that showing only the work in prgress. Best regards Mike T.
Member for
19 years 7 monthsDariusz,You can if you make a
Dariusz,
You can if you make a small compromise and that is not showing the completed tasks under an incomplete summary.
The filter would be
[[wysiwyg_imageupload:8036:]]
Criteria 1 - Summary Tasks with Task Progress Completed
Criteria 2 - Tasks or Milestones or Summary Tasks with Task Progress Specific Progress Amount Less Than 100%
Also, Objects must meet ANY criteria
Otherwise, I'm sure you could write an SQL statement but not sure I can help you with that.
Let me know if that works for you.
Kind regards,
Konstantinos
Member for
19 years 10 monthsSorry DariuszYou have to do
Sorry Dariusz
You have to do it manually.
One Click and save is all you need.
You don't have to show all your sub tasks.
You can have a sub summary labelledd 100% and move every complted task down into that showing only the work in prgress.
Best regards
Mike T.