where 

Start equals DD+1m

and then review your results 

Member for

22 years 9 months

Hi Rod,

if you want to use this formula in a lag between two activities, make sure to check the scheduling options: by default, the lag will use the predecessor's calendar, and yoy can choose the successor's, the default calendar or a 24h/d calendar

Alexandre

Member for

19 years

Depends on where are you using the formula. If using in Filter it calculates using the default calendar working days. If using on the report Page set-up option then it use the calendar days.

Member for

21 years

Easy to check it out. Run a global change and set a UDF to your formula!