Multi-schedule Program Summary Bar Cost Buckets - what does not work, what does? PPM vs EPPM vs cloud

Member for

16 years 3 months

you can also use a LOE but make sure that you assign a resource curve to the resource on the LOE or it wil stack all units and or costs for that resource for that LOE on the data date

Member for

19 years

Of course you can assigned resources and cost to any of Primavera (P6) Platform on activity type WBS Summary activities. Please note that WBS Summary activities are ignored during the leveling process because the WBS summary activities dates is driven by WBS activity elements under the same WBS.