P6 Professional R19.12 Import Resource Assignment from Excel

Member for

8 years 7 months

Rodel,

Okay, thanks, tools | recalculate assignment costs worked.

 

--Steve

Member for

21 years

Steve,

You need to check the default rate that new resource allocations use, which is in the 'Resources' tab at the project level. If you do not specify which rate to use on the Export/Import process (you can) , that is the one it will use.

Member for

19 years

Hi Steve,

I already explained to you why you are getting Price/Unit $1.00/h^. If you have the price/unit setup and after the import still showing Price/Unit = $1.00/h^ but having the correct amount, it means that you have not refresh the schedule assignment cost. To refresh, On the menu under Tools, select "Recalculate Assignment Cost" and a window pop-up will show as per sample below.

Recalculate-Assignment-Cost

Click Recalculate and the assignment cost will be refresh.