Have you tried to add a BL2 Duration UDF of data type Number or Integer and then apply a Global Change (BL2 Finish - BL2 Start) to calculate your BL2 Duration?
Downside of this workaround is that your WBS BL2 Duration will be wrong since UDF of Number/Integer types are summed.
Project Baseline is the baseline project that all users see when they open the project. BL1 and BL2 are specific to each user and the fields that P6 calculates for BL1 and BL2 is not as extensive as for Project Baseline.
Member for
21 years 9 monthsAntony,Have you tried to add
Antony,
Have you tried to add a BL2 Duration UDF of data type Number or Integer and then apply a Global Change (BL2 Finish - BL2 Start) to calculate your BL2 Duration?
Downside of this workaround is that your WBS BL2 Duration will be wrong since UDF of Number/Integer types are summed.
=jerome
PlannersPlace.com
Member for
20 years 6 monthsP6 can't show BL2 Durations,
P6 can't show BL2 Durations, only BL1.
Project Baseline is the baseline project that all users see when they open the project. BL1 and BL2 are specific to each user and the fields that P6 calculates for BL1 and BL2 is not as extensive as for Project Baseline.