Oracle Primavera - PM6 Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Thu, 2021-04-01 19:09 Permalink EV & Performance % Complete EV & Performance % Complete in Primavera P6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2021-03-30 14:31 Permalink no they ar enot linked what no they ar enot linked what you can do is creat a global chnage where the duration % complete is equal to the physical % complete. Here is how got to tools global change on the right select new Where Physcial % is not equal to 0 Then Duration % Complete = Physical % Complete on the right select Change then on the bottom right select Commit Changes Log in or register to post comments
Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Thu, 2021-04-01 19:09 Permalink EV & Performance % Complete EV & Performance % Complete in Primavera P6
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2021-03-30 14:31 Permalink no they ar enot linked what no they ar enot linked what you can do is creat a global chnage where the duration % complete is equal to the physical % complete. Here is how got to tools global change on the right select new Where Physcial % is not equal to 0 Then Duration % Complete = Physical % Complete on the right select Change then on the bottom right select Commit Changes
Member for
21 years 8 monthsEV & Performance % Complete
EV & Performance % Complete in Primavera P6
Member for
16 years 3 monthsno they ar enot linked what
no they ar enot linked what you can do is creat a global chnage where the duration % complete is equal to the physical % complete.
Here is how
got to tools
global change
on the right select new
Where Physcial % is not equal to 0
Then
Duration % Complete = Physical % Complete
on the right select Change
then on the bottom right select Commit Changes