Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2021-03-25 13:41 Permalink glad I could help glad I could help Member for 5 years 6 months Member for 5 years 6 months Submitted by troon on Wed, 2021-03-24 14:59 Permalink Thanks a lot Zoltan Thanks a lot Zoltan Member for 5 years 6 months Member for 5 years 6 months Submitted by troon on Wed, 2021-03-24 14:53 Permalink Thanks a lot Zoltan Thanks a lot Zoltan Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2021-03-24 12:54 Permalink a Global chnage will not work a Global chnage will not work here export the physcial % complete and the Expense % complete to excel thne copy the physcial % complete to the expense complete and then import back into p6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2021-03-24 12:53 Permalink a Global chnage will not work a Global chnage will not work here export the physcial % complete and the Expense % complete to excel thne copy the physcial % complete to the expense complete and then import back into p6 Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2021-03-25 13:41 Permalink glad I could help glad I could help
Member for 5 years 6 months Member for 5 years 6 months Submitted by troon on Wed, 2021-03-24 14:59 Permalink Thanks a lot Zoltan Thanks a lot Zoltan
Member for 5 years 6 months Member for 5 years 6 months Submitted by troon on Wed, 2021-03-24 14:53 Permalink Thanks a lot Zoltan Thanks a lot Zoltan
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2021-03-24 12:54 Permalink a Global chnage will not work a Global chnage will not work here export the physcial % complete and the Expense % complete to excel thne copy the physcial % complete to the expense complete and then import back into p6
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2021-03-24 12:53 Permalink a Global chnage will not work a Global chnage will not work here export the physcial % complete and the Expense % complete to excel thne copy the physcial % complete to the expense complete and then import back into p6
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
5 years 6 monthsThanks a lot Zoltan
Thanks a lot Zoltan
Member for
5 years 6 monthsThanks a lot Zoltan
Thanks a lot Zoltan
Member for
16 years 3 monthsa Global chnage will not work
a Global chnage will not work here
export the physcial % complete and the Expense % complete to excel
thne copy the physcial % complete to the expense complete and then import back into p6
Member for
16 years 3 monthsa Global chnage will not work
a Global chnage will not work here
export the physcial % complete and the Expense % complete to excel
thne copy the physcial % complete to the expense complete and then import back into p6