there is no such Progress Period in MSP as in Primavera P6;
the Progress Line does not store the corresponding data in a field available to the user; therefore, as far as I know, you should use a numeric custom field to key in the Period Performance every time you display a Progress Line
a time consuming process if I can say, and MS Excel would be a more appropriate tool for that
Member for
22 years 9 monthsHi Cameron,there is no such
Hi Cameron,
there is no such Progress Period in MSP as in Primavera P6;
the Progress Line does not store the corresponding data in a field available to the user; therefore, as far as I know, you should use a numeric custom field to key in the Period Performance every time you display a Progress Line
a time consuming process if I can say, and MS Excel would be a more appropriate tool for that
Alexandre