installation rates should be based on estimated quantities and historial company standards also the number of men that are going to perfom the task.

I can have a task for 80 hours for 1 man to do something whoulcwould be 10 days. However if I put 2 men on that taks it will take 5 days.

It a combination of estimated manhours and the number of men to use on that task.