Hi Rafael,

If you have two projects open in Powerproject at the same time, you can simily copy-paste library items between the two files.

So if you have one project with all the reports nicely configured, you can open another project that does not have reports, then browse to the "Library Explorer" within both files.  Copy the folder of reports from the "good" project, and paste it into the target project.

All our example project templates and sample projects have some nice items pre-configured within them which users often move into thier own projects for future use.

Thanks,

Ben @ Powerproject

Member for

21 years 8 months

Even though I am not a Powerproject user it would be good to know the details of your solution for other users.  Maybe the reports can be saved to a file and you can share them as well if you post them to a file share server.  I would also like to see a PDF version of the reports, just one page should be enough.

Best Regards, Rafael

Member for

10 years 8 months

It was a very high level quality check looking at missing links, negative float etc. I was new the software so wasnt familiar with how to extract the info I needed. The first tender I looked at had all the standard reports enabled which was great and gave me exactly what I needed. Unfortunatley the other tenderers had disabled/removed these reports. I spoke to the vendor and they told me how to copy the reports between programmes so problem now solved.

Member for

10 years 8 months

It was a very high level quality check looking at missing links, negative float etc. I was new the software so wasnt familiar with how to extract the info I needed. The first tender I looked at had all the standard reports enabled which was great and gave me exactly what I needed. Unfortunatley the other tenderers had disabled/removed these reports. I spoke to the vendor and they told me how to copy the reports between programmes so problem now solved.

Member for

21 years 8 months

I do not know what you mean by a high level review; superficial, thorough, in-between or by persons of high office or rank?  

Anyway any thorough review shall not only look for the obvious such as activity links, this would be the first step.

To name a few:

  • You should check for the activity durations as inflated durations are a way to sequester float. Requiring resource loading of activities can help to detect activity duration bloating. 
  • Calendars shall be checked with the understanding calendars are not only about work week but also about calendar exceptions.  Most software are bad at disclosing calendar exceptions database to the extreme the only way you can find them is to scroll the calendars, schedulers know it and can take advantage of this.
  • Any changes among schedule versions should be reviewed, there are literally thousands of parameter values that can be changed by schedulers when submitting their schedule updates.  Instead of importing the full schedule updates importing only the performance data would prevent hidden unauthorized changes.

Member for

21 years 8 months

If your software provides a Links Table then use it.  The table is very convenient to show and filter all links parameters as there are many of them. If using Monte Carlo then numeric values might not be deterministic and these can be of interest. Transferring the table to Excel is convenient for those who do not have access to the source file, they will be able to sort and filter, better than a static report.

Image-039

https://help.elecosoft.com/powerproject/english/15.0.02/Content/HTML_Topics/Conceptual/Producing_reports/Producing_reports.htm

https://help.elecosoft.com/powerproject/english/15.0.02/Content/HTML_Topics/Conceptual/Producing_reports/Business_Intelligence/Export_to_BI.htm