Sort by Project in Activity View

Member for

18 years 8 months

Hi All,

I also found that if you get the project in the correct order in the project view using the project ID as the sort then sort the WBS alphabetically in the activity view they go to the same order as the project view.

Thanks

Member for

21 years

Sorry, that no longer works. It is OK in the activity window, but not the project window. They have had twnty years to get this right. I shall report back if I find a way to properly order projects in version 19

Member for

21 years

With all the projects open, go to the WBS window, Collapse All, and just move them up and down with CTRL-arrow key.

Thanks Oracle, you changed that keystroke sequence. Took me 20 minutes.

Member for

20 years 6 months

Try making the first row of your grouping as "EPS/WBS" and uncheck the Indent box.