I'm actually interested in full forensic comparison rather than simply referencing baseline dates - I understand Elecosoft has an add on called Project Comparison? Is that what you use, and if so what do you think of it compared to say Acumen Fuse? or are there other options?
I'm actually interested in full forensic comparison rather than simply referencing baseline dates - I understand Elecosoft has an add on called Project Comparison? Is that what you use, and if so what do you think of it compared to say Acumen Fuse? or are there other options?
Member for
12 years 2 monthsThanks Mike,I'm actually
Thanks Mike,
I'm actually interested in full forensic comparison rather than simply referencing baseline dates - I understand Elecosoft has an add on called Project Comparison? Is that what you use, and if so what do you think of it compared to say Acumen Fuse? or are there other options?
Regards, Tim
Member for
12 years 2 monthsThanks Mike,I'm actually
Thanks Mike,
I'm actually interested in full forensic comparison rather than simply referencing baseline dates - I understand Elecosoft has an add on called Project Comparison? Is that what you use, and if so what do you think of it compared to say Acumen Fuse? or are there other options?
Regards, Tim
Member for
19 years 10 monthsHi TimEvery base date for
Hi Tim
Every base date for progress is recorded within the software so that you can trace progress from strt to finish.
THis is invaluable when tracking progress for an EOT claim As Built record.
Good luck with the switch, you won't regret it.
Best regards
Mike Testro