Update Baseline

Member for

5 years 1 month

David, thank you very much for the help. We found an article on the Oracle P6 Support page that addressed the problem we were having, the link to the article is below. Turns out we needed to install a patch. The patch set was P6 EPPM R19.12.5.0. Update Baseline is now working. Thanks again.

https://support.oracle.com/epmos/faces/DocContentDisplay?_afrLoop=383179889479816&id=2677828.1&_afrWindowMode=0&_adf.ctrl-state=1654lrc4mf_250

Member for

21 years

version 19 should be good. It works here

It’s a bit late now, but the way I would have avoided the problem is this:

ALL growth in scope goes into at least one separate project, which has “current project” as the basis for EV calculations. This means they have their own “Planned “dates as BL1 or Project Baseline dates, and earn value without having a baseline, which is a weird idea for growth anyway. When Base and Growth projects are open together, relationships can be drawn between the activities, and the single schedule calculated. If you open just the Base project, you can tick the “ignore relationship to other projects” button in the scheduling options, and see the schedule with no growth.

Of course, with all the projects open, P6’s ridiculous Project-specific WBS code looks, well, ridiculous. The corporate WBS should always be a Global Activity code.

Member for

5 years 1 month

Thank you for the posts.

Here is the P6 version: Primavera P6 Professional 19, 19.12.0.34128

I tried restoring the updated baseline, scheduling the updated baseline, then assigning the updated baseline back to the project as a baseline. This did not work.

I tried restoring the updated baseline, scheduling the updated baseline, restarting the computer, scheduling the updated baseline, then assigning the updated baseline back to the project as a baseline. This did not work.

We are going to contact the P6 reseller to see if they can help, and if not, if they can contact Oracle to get a solution. If we are able to solve the problem I will post the solution.

I am still open to and interested in other ideas you might have for how to make it work..

Thank you.

Member for

16 years 3 months

go project then maintina baseline

the select Update

here you can choose to add new activies to the baseline

Member for

21 years

Version of P6? - update Baseline is well dodgy prior to V16.

Member for

15 years 11 months

Hi,

I suggests the following:

1. Restore the Updated Baseline and Schedule then assign back.

2. Restarting P6 or the Computer for the Database to Refresh.

Hopes this will help.