Oracle Primavera - PM6 Member for 24 years 8 months Member for 24 years 9 months Submitted by Vladimir Liberzon on Fri, 2020-10-09 21:04 Permalink John,cost and schedule are John, cost and schedule are closely integrated. Changing schedule we change project budget, financial constraints impact project schedule. We manage both using the same tool. Why do you need something external to your scheduling software? What exactly is not supported by your scheduling tool? Log in or register to post comments
Member for 24 years 8 months Member for 24 years 9 months Submitted by Vladimir Liberzon on Fri, 2020-10-09 21:04 Permalink John,cost and schedule are John, cost and schedule are closely integrated. Changing schedule we change project budget, financial constraints impact project schedule. We manage both using the same tool. Why do you need something external to your scheduling software? What exactly is not supported by your scheduling tool?
Member for
24 years 8 monthsJohn,cost and schedule are
John,
cost and schedule are closely integrated.
Changing schedule we change project budget, financial constraints impact project schedule.
We manage both using the same tool. Why do you need something external to your scheduling software?
What exactly is not supported by your scheduling tool?