Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2020-08-21 15:34 Permalink agree 5 days is a working agree 5 days is a working calendar Member for 21 years 3 months Member for 21 years 4 months Submitted by Danya on Thu, 2020-08-20 07:51 Permalink Unless you are working 7 Unless you are working 7 days, keep it on a 5 day calendar. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2020-08-21 15:34 Permalink agree 5 days is a working agree 5 days is a working calendar
Member for 21 years 3 months Member for 21 years 4 months Submitted by Danya on Thu, 2020-08-20 07:51 Permalink Unless you are working 7 Unless you are working 7 days, keep it on a 5 day calendar.
Member for
16 years 3 monthsagree 5 days is a working
agree 5 days is a working calendar
Member for
21 years 3 monthsUnless you are working 7
Unless you are working 7 days, keep it on a 5 day calendar.