John – “My assumption would be there is something un-completed in the chain but that is not checking out.”
Agree – maybe a driving link with some remaining lag.
Zoltan – “If an activity is complete there is no float. The only way that there would be a late date is if there is not an ACTUAL start or ACTUAL finish.”
Agree, in any case it is on active links/relationships that there might be some “float” or “slack”.
if an activity is completed there is no longer a need for a late or early date. The difference between the early and late dates is the float. If an activity is complete there is no float. The only way that there would be a late date is if there is not an ACTUAL start or ACTUAL finish.
Member for
21 years 8 monthsJohn – “My assumption would
John – “My assumption would be there is something un-completed in the chain but that is not checking out.”
Zoltan – “If an activity is complete there is no float. The only way that there would be a late date is if there is not an ACTUAL start or ACTUAL finish.”
https://www.linkedin.com/pulse/relationship-float-viewing-primavera-p6-santosh-bhat
Most software does not show early/late dates for completed activities. I cannot see a reason to show meaningless values.
Member for
16 years 3 monthsif an activity is completed
if an activity is completed there is no longer a need for a late or early date. The difference between the early and late dates is the float. If an activity is complete there is no float. The only way that there would be a late date is if there is not an ACTUAL start or ACTUAL finish.