on tracking

Member for

20 years 7 months

Few more...



Schedules are mainly tracked on three things



1)Time

2)Resources i.e. Man, Material,Money

3)Site Inspection



The presentation of the these parameters can be done in many forms depending on the level at which are to be presented.


Member for

22 years 7 months

Tracking:



1. Establish baseline programme.

2. Distribute monitoring sheets to relevant supervisors(capture the relevant information you need to update schedule)

3. Set up the periodical updating date before which u need to receive the item 2.

4. Update the schedule(use baseline your target to check for any slippages)



in the next update, use the prev. update as your one of target schedule to verify any activities slipped from the completion dates, check over all project completion date...



many more things to add............




Member for

20 years 8 months

Hi,



What do you mean by HOW TO DO THE TRACKING IN A PROJECT?

Is it MS Project schedule or P3e schedule.



Regards.

Member for

23 years 8 months

Francis,

Brochures and lot of application cases are available on Primavera website.