Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2020-05-12 16:26 Permalink Ilia,"Merge the data into the Ilia, "Merge the data into the active project" Alexandre Member for 15 years 5 months Member for 15 years 5 months Submitted by Ilia Baranov on Tue, 2020-05-12 13:20 Permalink Thanks Alexandre! But i need Thanks Alexandre! But i need a correct options for dialog bох? Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2020-05-12 12:38 Permalink Hello Iliapresuming the Hello Ilia presuming the actual data to be imported are stored in an Excel file with the MS Project Export/import format, open the file to be updated in MS Project, select the Excel file in the MS Project File, Open dialog, select the Update project option Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2020-05-12 16:26 Permalink Ilia,"Merge the data into the Ilia, "Merge the data into the active project" Alexandre
Member for 15 years 5 months Member for 15 years 5 months Submitted by Ilia Baranov on Tue, 2020-05-12 13:20 Permalink Thanks Alexandre! But i need Thanks Alexandre! But i need a correct options for dialog bох?
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2020-05-12 12:38 Permalink Hello Iliapresuming the Hello Ilia presuming the actual data to be imported are stored in an Excel file with the MS Project Export/import format, open the file to be updated in MS Project, select the Excel file in the MS Project File, Open dialog, select the Update project option Alexandre
Member for
22 years 9 monthsIlia,"Merge the data into the
Ilia,
"Merge the data into the active project"
Alexandre
Member for
15 years 5 monthsThanks Alexandre! But i need
Thanks Alexandre! But i need a correct options for dialog bох?
Member for
22 years 9 monthsHello Iliapresuming the
Hello Ilia
presuming the actual data to be imported are stored in an Excel file with the MS Project Export/import format,
open the file to be updated in MS Project,
select the Excel file in the MS Project File, Open dialog,
select the Update project option