I thought of that but it's so small I can't actually read it. I can't seem to find a way of zooming the view to make it readable with the amount of predecessors some activities have and I can't seem to be able to print it to read elsewhere.
Is there a way you know of being able to do either of these?
Thanks,
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2020-05-08 14:59
the other option is to create a activity code and name it mypath and give it a code value of CP
now filter for the last activity
go to the predcessor tab and if the driving and critical boxes are not there then in the predcessor window right click and select customize predcessor columns
expand the General category and bring both the DRIVING and CRITICAL categories to the right
no look for the predcessor activity that has BOTH the driving and the critical boxes checked
now click on that predcessor and at the bottom of the window select GOTO
keep doing this until you get back to the data date.
now select all of the activities
then rigth click and select assign and select activity codes and select the newly added code of mypath and give them the code value of CP
now you can filter for activity code where mypath = CP and see the driving activities.
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Thu, 2020-05-07 19:27
Be reminded that Longest Path miserably fails at resource leveled schedules. As you can see in the following sample schedule most activities are not linked but their use/consumption of resources will delay other activities.
not resource leveled schedule
resource leveled schedule
resource dependencies shown
Note while resource dependencies are shown for renewable resources, dependencies for materials[consumable resources] are not.
When this happens Longest Path breaks and will not tell you the reason for activity delay, a very convenient field available in Spider Project. I wonder how P6 users answer this question when the schedule is resource leveled.
Schedule calculation options, Advanced, Calculate multiple float paths, free float, ending with your selected activity, no limit on number of paths to calculate. Then group by Float Path and sort by Float Path Order. done.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2020-04-30 13:44
Member for
16 years 3 monthsI have developed 3 day
I have developed 3 day training program and I teach in house Project managers, Project Engineers, superintendendts and foremen.
Its a 400 page manual with screen shots where you can basically teach yourself withe manual. I have taught over 300 people.
Member for
19 years 1 monthZoltan as always amazing.
Zoltan as always amazing. Have you thought about running training courses?
thank you once again for digging me out of a hole. :)
Member for
15 years 11 monthsHi Thomas,As suggested by
Hi Thomas,
As suggested by Zoltan, Use the Filter Critical and Longest Path together but make sure to select "All selected filters" above the filter pane.
Then View from the the Gantt Chart to trace the Driving Activity along the Longest path.
Hope this will help.
Member for
19 years 1 monthHi Raymond, I thought of that
Hi Raymond,
I thought of that but it's so small I can't actually read it. I can't seem to find a way of zooming the view to make it readable with the amount of predecessors some activities have and I can't seem to be able to print it to read elsewhere.
Is there a way you know of being able to do either of these?
Thanks,
Member for
16 years 3 monthschose both filters critical
chose both filters critical AND LONGEST path
the other option is to create a activity code and name it mypath and give it a code value of CP
now filter for the last activity
go to the predcessor tab and if the driving and critical boxes are not there then in the predcessor window right click and select customize predcessor columns
expand the General category and bring both the DRIVING and CRITICAL categories to the right
no look for the predcessor activity that has BOTH the driving and the critical boxes checked
now click on that predcessor and at the bottom of the window select GOTO
keep doing this until you get back to the data date.
now select all of the activities
then rigth click and select assign and select activity codes and select the newly added code of mypath and give them the code value of CP
now you can filter for activity code where mypath = CP and see the driving activities.
Member for
15 years 11 monthsI suggest to use the Trace
I suggest to use the Trace Logic Chart and change the Options to see numbers of Predecessors and Filter to Critical.
Member for
19 years 1 monthHi Zoltan, Unfortunately I
Hi Zoltan,
Unfortunately I don’t have driving as an option for a filter.
Thanks as always for the advice though.
Member for
19 years 1 monthHi Tom, They may do
Hi Tom,
They may do something but I can’t see it showing me any difference to export the info in a useful fashion for my team.
Thanks for the advice though.
Member for
21 years 8 monthsBe reminded that Longest Path
Be reminded that Longest Path miserably fails at resource leveled schedules. As you can see in the following sample schedule most activities are not linked but their use/consumption of resources will delay other activities.
Note while resource dependencies are shown for renewable resources, dependencies for materials[consumable resources] are not.
When this happens Longest Path breaks and will not tell you the reason for activity delay, a very convenient field available in Spider Project. I wonder how P6 users answer this question when the schedule is resource leveled.
Member for
18 years 11 months(duplicate)
(duplicate)
Member for
18 years 11 monthsSchedule calculation options,
Schedule calculation options, Advanced, Calculate multiple float paths, free float, ending with your selected activity, no limit on number of paths to calculate. Then group by Float Path and sort by Float Path Order. done.
Member for
16 years 3 monthsfilter for driving AND
filter for driving AND critical