1. some people track non resource cost as expenses and can be categorized as many differen thing are usually project specific such as facilities, travel overhead and training. This like a resource can be show to occur at the start or end of the activity or spread over the duration of the activity.
2. you can set up different resource and assing the costs and use a custom curve for distribution of those costs
3. ususally the % complete is your monthly invoice. You can not put dollar on a milestone because a milestones can not have a resource. Revenue should be your invlove. You budgeted amounts should equal your total cost for the project and should include profit and overhead as well.
4. Yes you can select view show on bottom resource usage profile and selct which curves to show inclusing budgeted and actual. You actual will be your client invoicng.
Member for
16 years 3 months1. some people track non
1. some people track non resource cost as expenses and can be categorized as many differen thing are usually project specific such as facilities, travel overhead and training. This like a resource can be show to occur at the start or end of the activity or spread over the duration of the activity.
2. you can set up different resource and assing the costs and use a custom curve for distribution of those costs
3. ususally the % complete is your monthly invoice. You can not put dollar on a milestone because a milestones can not have a resource. Revenue should be your invlove. You budgeted amounts should equal your total cost for the project and should include profit and overhead as well.
4. Yes you can select view show on bottom resource usage profile and selct which curves to show inclusing budgeted and actual. You actual will be your client invoicng.