Transfer Progress between 2 Programmes

Member for

16 years 3 months

1. thats becasue a TRUE baseline does not have progress or actual start and finish dates NO PROGRESS.

2. I am not sure why you are not using the method that I suggedted

3. Export the newer progress schedule to excel then import this into the lesser progress schedule. You wil have to change the first few characters of the wbs column in excel to match the project ID of the lesser progress scheduel prior to importing it. 

i.e. Project ID of exported greater progress schedule is called CARSUPDATE5

i.e. Project ID of less progress schedule is called CARSUPDATE3

in the excel file change the wbs column to CARSUPDATE3

Member for

14 years 9 months

Hi Zoltan, 

 

Thank you for the reply. 

 

I am working on a test, created

Is there a way i can use Global Change to reflect the progress to Baseline? 

 

Please see below, 

 

I want to create

Actual Start = Baseline Actual Start (Doesnt really work even after i use the global change) 

Actual Finish = Baseline Actual Finish (Doesnt really work even after i use the global change) 

Duration % Complete = BL Duration % Complete (cannot find this option)

Physical % Complete = BL Physical % Complete (cannot find this option)

 

Do you think there is a way to use the global change? If not, then maybe i have to work on the hard way, type in the progress manually... 

 

Many thanks

Mike 

 

[[wysiwyg_imageupload:7342:]]

Member for

16 years 3 months

assign the one with less progress as baseline then select maintain baselines and on the rigth select Update

now you can choose what you want updated on the project with the less progress

after you are done unassign the basline and select restore