Microsoft Project Member for 16 years 11 months Member for 16 years 11 months Submitted by Angelito Estrella on Mon, 2020-07-13 05:42 Permalink Alt+Shift+Right Arrow Alt+Shift+Right Arrow Member for 13 years 2 months Member for 13 years 2 months Submitted by nahla nour on Sun, 2020-04-05 04:19 Permalink Did you resolve your issue ? Did you resolve your issue ? Member for 13 years 2 months Member for 13 years 2 months Submitted by nahla nour on Sun, 2020-04-05 04:15 Permalink Hi Nathan,Could you please Hi Nathan, Could you please put a screnshot of your workplan, just to understand the issue, Regards, Mar Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2020-03-20 17:04 Permalink Nathan,I hope this will help Nathan, I hope this will help you: on image natan1, select Task B and click the tool inside the red square you should obtain the result in image nathan2.png alexandre [[wysiwyg_imageupload:7326:]] [[wysiwyg_imageupload:7327:]] Member for 11 years 6 months Member for 11 years 6 months Submitted by vanmiganathan on Fri, 2020-03-20 11:30 Permalink Hi Alexandre,Thanks for your Hi Alexandre, Thanks for your suggestion, But I'm still facing the same issue, even after I used indent tool, it's not showing any changes in outline level. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2020-03-20 10:34 Permalink Hi NathanI am not sure to Hi Nathan I am not sure to understand where your problem stands; let's do the following select the second task in the spreadsheet, then in the Task tab of the ribbon click on the Indent tool (the small arrow looking to the right) as far as I know there is no functionnality ins MS Project to disable indenting/oudenting tasks in a project All the best, Alexandre Log in or register to post comments
Member for 16 years 11 months Member for 16 years 11 months Submitted by Angelito Estrella on Mon, 2020-07-13 05:42 Permalink Alt+Shift+Right Arrow Alt+Shift+Right Arrow
Member for 13 years 2 months Member for 13 years 2 months Submitted by nahla nour on Sun, 2020-04-05 04:19 Permalink Did you resolve your issue ? Did you resolve your issue ?
Member for 13 years 2 months Member for 13 years 2 months Submitted by nahla nour on Sun, 2020-04-05 04:15 Permalink Hi Nathan,Could you please Hi Nathan, Could you please put a screnshot of your workplan, just to understand the issue, Regards, Mar
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2020-03-20 17:04 Permalink Nathan,I hope this will help Nathan, I hope this will help you: on image natan1, select Task B and click the tool inside the red square you should obtain the result in image nathan2.png alexandre [[wysiwyg_imageupload:7326:]] [[wysiwyg_imageupload:7327:]]
Member for 11 years 6 months Member for 11 years 6 months Submitted by vanmiganathan on Fri, 2020-03-20 11:30 Permalink Hi Alexandre,Thanks for your Hi Alexandre, Thanks for your suggestion, But I'm still facing the same issue, even after I used indent tool, it's not showing any changes in outline level.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2020-03-20 10:34 Permalink Hi NathanI am not sure to Hi Nathan I am not sure to understand where your problem stands; let's do the following select the second task in the spreadsheet, then in the Task tab of the ribbon click on the Indent tool (the small arrow looking to the right) as far as I know there is no functionnality ins MS Project to disable indenting/oudenting tasks in a project All the best, Alexandre
Member for
16 years 11 monthsAlt+Shift+Right Arrow
Alt+Shift+Right Arrow
Member for
13 years 2 monthsDid you resolve your issue ?
Did you resolve your issue ?
Member for
13 years 2 monthsHi Nathan,Could you please
Hi Nathan,
Could you please put a screnshot of your workplan, just to understand the issue,
Regards,
Mar
Member for
22 years 9 monthsNathan,I hope this will help
Nathan,
I hope this will help you:
on image natan1, select Task B and click the tool inside the red square
you should obtain the result in image nathan2.png
alexandre
[[wysiwyg_imageupload:7326:]]
[[wysiwyg_imageupload:7327:]]
Member for
11 years 6 monthsHi Alexandre,Thanks for your
Hi Alexandre,
Thanks for your suggestion, But I'm still facing the same issue, even after I used indent tool, it's not showing any changes in outline level.
Member for
22 years 9 monthsHi NathanI am not sure to
Hi Nathan
I am not sure to understand where your problem stands;
let's do the following
select the second task in the spreadsheet, then in the Task tab of the ribbon click on the Indent tool (the small arrow looking to the right)
as far as I know there is no functionnality ins MS Project to disable indenting/oudenting tasks in a project
All the best,
Alexandre