As built programme

Member for

20 years 7 months

Hi, Mike. Since Asta Powerproject, unlike Primavera, has the ability to compute critical path drag, can I suggest two more columns?

1. As Planned drag.

2. As Built drag.

I also think that tracking changes in drag for each activity (especially when the CP changes causing different activities to have drag) with each new version of the schedule during execution would be VERY valuable from a forensic viewpoint -- but admittedly, that gets a bit more complicated.

Fraternally in project management,

Steve the Bajan

Member for

19 years 10 months

Hi Chris

Save the file inot a new one.

Transfer all of your weekly progress reports onto a spreadsheet.

Add 2 new columns Start AB plus End AB and transfer the 1st record above 0 and the last record at 100.

You can get accurate dates by interpolating % complete on the days of the month.

Set up your As planned bars as a baseline and then copy/paste your spreadsheet dates into the Start and Finish columns.

You now have an As Planned v As Built comparison programme.

Best regards Mike Testro.