When a start-to-start relationship exists and the predecessor starts out of sequence, the successor activity is delayed until that expires and all predecessor relationships have been satisfied. You can choose to subtract the lag from the predecessor's actual start date or its internal early start date. See Start to start relationship.
Choose Actual Start when you want the successor's start to depend on the time elapsed from the predecessor's actual start (regardless of the amount of work that has been accomplished in the predecessor activity). The successor's start date is the data date plus any remaining lag.
Choose Early Start when the successor's start depends on the amount of work that the predecessor activity accomplishes. The expired lag is calculated as the number of workperiods between the actual start and the data date. The successor's start date is the predecessor's internal early start plus any remaining lag.
Member for
15 years 8 monthsHi there,I wrote an article
Hi there,
I wrote an article to explain these options.
Kindly read it here https://doduykhuong.com/2020/01/26/primavera-p6-schedule-options-calculate-start-to-start-lag-from/
Regards,
Khuong
Member for
11 years 3 monthsHi, When a start-to-start
Hi,
When a start-to-start relationship exists and the predecessor starts out of sequence, the successor activity is delayed until that expires and all predecessor relationships have been satisfied. You can choose to subtract the lag from the predecessor's actual start date or its internal early start date. See Start to start relationship.
Choose Actual Start when you want the successor's start to depend on the time elapsed from the predecessor's actual start (regardless of the amount of work that has been accomplished in the predecessor activity). The successor's start date is the data date plus any remaining lag.
Choose Early Start when the successor's start depends on the amount of work that the predecessor activity accomplishes. The expired lag is calculated as the number of workperiods between the actual start and the data date. The successor's start date is the predecessor's internal early start plus any remaining lag.
- Ravi