NO that makes no sense at all. Your actulas are your actuals you can not change that is history and reflects what has actually happened. Now take that schedule and forecast the remaining work from now forward and make sure you finish the scheduel reflects completion on or before that contractual completin date. This is the REVISED BASELINE.
I'v been discussing this issue for a long time with one of my collegues, the reason why i posted it here. He told me that a baseline with actual progress and activities status marked as started caused him later on a problem in the database in a previous project.As a result, he lost his database. since then he started adjusting the new baseline to meet at first the actual dates by modifying relatiionships and lags, and then the remaining activiities to respect the contractual finish date
Thanks Folks
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2020-01-22 14:33
You can create a new baseline with the progressed project; this way, you will keep the original baseline with the non-progressed project, and you will be able to compare the current status of the project with both the original and the new baseline.
Otherwise, you could update the original baseline if the functionnality is available (some P6 versions with the SQLlite database do not have this functionnality)
In my opinion, removing the actuals before saving a new baseline is not an option.
Member for
10 years 2 monthsCheck My Post
Check My Post Here.
https://youtu.be/pxax6hlolvE
Member for
16 years 3 monthsNO that makes no sense at
NO that makes no sense at all. Your actulas are your actuals you can not change that is history and reflects what has actually happened. Now take that schedule and forecast the remaining work from now forward and make sure you finish the scheduel reflects completion on or before that contractual completin date. This is the REVISED BASELINE.
Member for
5 years 9 monthsThanks for your clarification
Thanks for your clarification
Member for
5 years 9 monthsAlexandre-I'v been discussing
Alexandre-
I'v been discussing this issue for a long time with one of my collegues, the reason why i posted it here. He told me that a baseline with actual progress and activities status marked as started caused him later on a problem in the database in a previous project.As a result, he lost his database. since then he started adjusting the new baseline to meet at first the actual dates by modifying relatiionships and lags, and then the remaining activiities to respect the contractual finish date
Thanks Folks
Member for
16 years 3 monthsyou must re-baseline with
you must re-baseline with actuals this is your new line in the sand.
Member for
22 years 9 monthsAbderrahim,You can create a
Abderrahim,
You can create a new baseline with the progressed project; this way, you will keep the original baseline with the non-progressed project, and you will be able to compare the current status of the project with both the original and the new baseline.
Otherwise, you could update the original baseline if the functionnality is available (some P6 versions with the SQLlite database do not have this functionnality)
In my opinion, removing the actuals before saving a new baseline is not an option.
Alexandre