In P6, each project requires its own baseline project (set under PROJECT>MAINTAIN BASELINES), and then you have to one-by-one for each project select which is the Project, Primavera, Secondary etc. baseline project.
Bear in mind that baselines are displayed by comparing Activity ID, you need the same ID in both the current and the baseline project for the baseline bar/milestone to be displayed.
In your example, if all your LOE's and and milestones are in one single project anyway, you could just create baselines of this one project with each of the LOE/Milestones showing the "past" date you want to show.
Member for
16 years 3 monthsglad i could help
glad i could help
Member for
6 years 9 monthsI like this! Thanks!
I like this! Thanks!
Member for
16 years 3 monthsif you are just showing LOE
if you are just showing LOE then do this
copy the project
filter where activity type not equal to LOE
next deleted all these activiites (all you are left with are the LOE activities)
now change all of the Actvitiy type to Task Dependent
for all of these add a primary constraint START ON and make the date equal to the planned start date
for all of these add and expcted finish constraint equal to whatever the date was originally
recalcute the schedule chnanging the data date to whatever the baseline data date was
now go into your current schedule select Project Maintain Baselines and selet Add and select the project you just created
now selet Project assign baseline and select the project that you just created
now filter where activity type eqauls LOE
now right click in the gantt area and select bars
in the bar setting make sure to show the Primary Baseline bar
DONE
Member for
6 years 9 monthsExcellent!! I was going down
Excellent!! I was going down that line but wanted validation before I spent too much work. Thanks!! Greatly appreciated!
Member for
20 years 6 monthsIn P6, each project requires
In P6, each project requires its own baseline project (set under PROJECT>MAINTAIN BASELINES), and then you have to one-by-one for each project select which is the Project, Primavera, Secondary etc. baseline project.
Bear in mind that baselines are displayed by comparing Activity ID, you need the same ID in both the current and the baseline project for the baseline bar/milestone to be displayed.
In your example, if all your LOE's and and milestones are in one single project anyway, you could just create baselines of this one project with each of the LOE/Milestones showing the "past" date you want to show.